Construction Chronology |
Job Site Milestones |
|
|---|---|
| Phase I -- Construction of Tower, Floors 4 through 8 | |
| Notice to Proceed | Jan. 23, 1995 |
| Groundbreaking Ceremony | Jan. 27, 1995 |
| Start of Foundation | May 1, 1995 |
| Start of Superstructure | Jun.7, 1995 |
| Complete Structure through Existing Building | Dec. 20, 1995 |
| Complete Superstructure | May 7, 1996 |
| Building Closed-In | Dec. 15, 1996 |
| Breezeway Completed | Jan. 5, 1997 |
| Library Move-In | Feb. 18, 1997 |
| Phase II -- Renovation & Expansion of Floors 1,2, 3 | |
| Excavation Work-East & West Sides | Oct. 21, 1996 |
| Start Footings | Nov. 10, 1996 |
| Start Demolition | Feb. 24, 1997 |
| Start Architectural Precast | July 16, 1997 |
| Complete Superstructure | Aug. 22, 1997 |
| Conditioned Air Available | Oct. 30, 1997 |
| Building Closed-In | Nov. 15, 1997 |
| Library Move-In | Apr. 24, 1998 |
Quantitative Analysis |
|
|---|---|
| Yards of fill excavated for new foundation | 2,200 yd 3 |
| Number of new piles added to support tower | 341 |
| Yards of concrete poured | 17,000 yd 3 |
| Tons of reinforcing steel used | 1,430 tons |
| Tons of refrigeration added | 978 tons |
| Pieces of precast used | 490 |
| Size of new switchgear service | 4,000 amps |
| Amount of new lay-in acoustical tile installed | 211,000 sf |
| Amount of new carpet installed | 29,000 yd 2 |
Information provided by Turner Construction Co.
Statistics |
|
|---|---|
| Area, net assignable | 227,957 ft. 2 |
| Collections, available space | 1,100,000 |
| Research carrels | 109 |
| Seating | 2000+ |
| Cost | $ 40,000,000+ |
May 4, 1998