Construction Chronology
& Statistics

Job Site Milestones

Phase I -- Construction of Tower, Floors 4 through 8
Notice to ProceedJan. 23, 1995
Groundbreaking Ceremony Jan. 27, 1995
Start of Foundation May 1, 1995
Start of Superstructure Jun.7, 1995
Complete Structure through Existing Building Dec. 20, 1995
Complete Superstructure May 7, 1996
Building Closed-In Dec. 15, 1996
Breezeway Completed Jan. 5, 1997
Library Move-In Feb. 18, 1997
Phase II -- Renovation & Expansion of Floors 1,2, 3
Excavation Work-East & West Sides Oct. 21, 1996
Start Footings Nov. 10, 1996
Start Demolition Feb. 24, 1997
Start Architectural Precast July 16, 1997
Complete Superstructure Aug. 22, 1997
Conditioned Air Available Oct. 30, 1997
Building Closed-In Nov. 15, 1997
Library Move-In Apr. 24, 1998

Quantitative Analysis

Yards of fill excavated for new foundation 2,200 yd 3
Number of new piles added to support tower 341
Yards of concrete poured 17,000 yd 3
Tons of reinforcing steel used 1,430 tons
Tons of refrigeration added 978 tons
Pieces of precast used 490
Size of new switchgear service 4,000 amps
Amount of new lay-in acoustical tile installed 211,000 sf
Amount of new carpet installed 29,000 yd 2

Information provided by Turner Construction Co.

Statistics

Area, net assignable 227,957 ft. 2
Collections, available space 1,100,000
Research carrels 109
Seating 2000+
Cost $ 40,000,000+

May 4, 1998